Serra de l'Ebre
Needs attentionCatalonia · Wind · 57 MW installed · 5 technicians · manager Firas Cheaib
8.1 MW
14 %
241 MWh
96.6 %
9 / 13
6
Wind
5.4 m/s ESE
Irradiance
170 W/m²
Temperature
20.5 °C
Cloud cover
63 %
Conditions
Partly cloudy
Substation
Ascó SE 400 kV
Voltage
400.0 kV
Frequency
50.005 Hz
Power factor
0.971
Curtailment
8 %
Day-ahead price
90.78 €/MWh
Assets
13 assets on site. Open one for its live 3D view.
Wind turbine
WTG-03
Siemens Gamesa SG 5.0-145 · 6.2 MW
Output
1.36 MW
Today
34.5 MWh
Wind
8.0 m/s
Wind turbine
WTG-04
Siemens Gamesa SG 5.0-145 · 5.0 MW
Output
0.21 MW
Today
26.9 MWh
Wind
5.7 m/s
Wind turbine
WTG-05
Siemens Gamesa SG 6.6-170 · 6.2 MW
Output
0.00 MW
Today
11.1 MWh
Wind
6.7 m/s
Wind turbine
WTG-07
Siemens Gamesa SG 5.0-145 · 5.0 MW
Output
0.00 MW
Today
32.4 MWh
Wind
9.7 m/s
Wind turbine
WTG-09
Siemens Gamesa SG 6.6-170 · 6.2 MW
Output
0.10 MW
Today
13.2 MWh
Wind
5.5 m/s
Wind turbine
WTG-10
Siemens Gamesa SG 6.6-170 · 4.2 MW
Output
2.65 MW
Today
18.7 MWh
Wind
10.8 m/s
Inverter skid
INV-01
Sungrow SG3125HV-MV · 4.6 MVA
Output
2.02 MW
Today
25.3 MWh
Availability
99.5 %
Inverter skid
INV-02
SMA Sunny Central 4600 UP · 3.1 MVA
Output
2.25 MW
Today
9.8 MWh
Availability
96.3 %
Blade ice detected
Generator winding temperature high
Yaw misalignment above limit
Pitch system hydraulic pressure low
Cooling fan failure
Service interval exceeded